The Station was exposed to an expired zinc roofing system, causing damage to the structural timber deck and in turn, decoration work to the underside canopy. The track-side guttering system had actually become dangerous, with parts of the gutter falling onto the track in severe weather conditions. The Stations main building tiled roof had also expired, requiring renewal to protect the newly renovated accommodations.
On our survey, it was noted that the existing system had failed to protect the canopy makeup and this led to further remedial work needed, including the complete removal of the existing structural deck coating and the installation of an additional Plywood Deck, to strengthen the canopy while providing a hard edge for the adhesion of the roofing system. The Stations main building roof also required suitable matching against the existing tiles, which were simply not manufactured anymore.